Reps query Chevron over $7.8 billion increase in cost of gas-to-liquids project

The committee on the Joint Venture of the NNPC limited raised concerns when the management of Chevron appeared before the lawmakers in Abuja.

• October 5, 2022
The House of Representatives Committee on Finance
The House of Representatives

An ad hoc committee of the House of Representatives has queried Chevron Nigeria Limited over the implementation of the Escravos gas-to-liquids (EGTL) gas project, which should cost $2.9 billion, but was quoted as $10.7 billion.

The committee on the Joint Venture of the NNPC limited raised concerns when the management of Chevron appeared before the lawmakers in Abuja.

The committee chairman, Hassan Fulata (APC-Jigawa), demanded an explanation and the reasons behind the review of the project’s cost from $2.9 billion to $10.7 billion, a $7.8 billion increase.

Mr Fulata said a similar project was executed in Qatar for less than $2.5 billion within a very short period, adding that NNPC should have protested the cost review and demanded a value-for-money audit.

Responding, Chevron’s director of joint venture, Monday Ovuede, told the committee that several factors caused the upward review of the project’s cost from the initial $2.9 billion to $10.7 billion.

Mr Ovuede explained that immediately after the project was signed, prices of commodities like oil and steel went up, necessitating an upward review of the project.

He added that Chevron agreed to a value-for-money audit despite not having it in the contract for the project.

“This is a very complex technology to be executed in this part of the world. When project construction started in 2005— coincidentally, if you check the record, commodity prices, including oil and steel, started rising in the international market. 

“The project was given as engineering, procurement and logistics, which means the sum was fixed. In the course of executing the contract, the contractors came back,” he said.

On the Qatar project, Mr Ovuede explained that the project was built in an industrial complex with a seaport and access to an international airbase. 

According to him, there was access to skilled labours compared to Nigeria, but such skills were hard to acquire.

“The plant in Qatar is built in an industrial complex close to a seaport, and there is an international airbase there.

“It has access to skilled labour from Europe, when you come to our side, we try to build—for some of the technology, we had to develop the local labour to the level required to implement the project,” he said.

Despite the explanations, the legislators remained dissatisfied and requested documents to back the claims.

Ibrahim Isiaka (APC-Ogun) moved a motion for Chevron to submit a written response justifying the increment.

In his ruling, Mr Fulata alleged that Chevron was claiming capital allowance for the project without capital importation or a certificate to make such a claim.

He ruled Chevron should appear again on Tuesday, October 11, with relevant documents to defend its claims.

(NAN)

We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.

More from Peoples Gazette

farmers

Agriculture

FG tasks ECOWAS on leveraging financing strategies for agroecology

The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Katsina State

Politics

Katsina youths pledge to deliver over 2 million votes to Atiku

“Katsina State is Atiku’s political base because it is his second home.”

Flooded Kaduna

States

Flooding: NEMA, KADSEMA search for missing persons in Kaduna River

NEMA and KADSEMA have launched a search-and-rescue operation for two persons swept away by floodwaters in the Kaduna River.

States

Police rescue 15 cows, one Katsina resident from bandits

The police command in Katsina says it has foiled kidnap and cattle rustling attempts in Funtua and Musawa council areas, rescuing one kidnap victim and recovering 15 rustled cows.

Nigeria Farmers

Agriculture

Farmers seek subsidised farm inputs to boost food production in Taraba

The farmers said the high cost and limited availability of fertilisers and other essential farm inputs had become major constraints as the rainy season commenced.

APC members

Politics

Kaduna: 12,000 people defect to APC in Lere LG

Twelve thousand members of opposition political parties have defected to the All Progressives Congress in the Lere council area of Kaduna.

Anti-Corruption

LS Cable & System USA agrees to pay $4 million to resolve PPP loan fraud allegations

LS Cable & System USA has agreed to pay $4 million to the United States to resolve allegations of false claims for payments under the Paycheck Protection Programme loans.

Anti-Corruption

U.S. census official sentenced to prison for bribery, fraud

The contract was worth millions of dollars. In exchange for steering the contract and modifications, Ms Jones received kickbacks from YMJ Consulting and the subcontractor.