FG’s unpaid debts stalled Calabar–Itu road rehabilitation, says contractor

Sematech Nigeria Ltd has attributed the slow pace of the rehabilitation of the Calabar-Itu road to unpaid debts.
The firm’s spokesman, Ita Asuquo, disclosed this in an interview in Calabar on Thursday.
Mr Asuquo spoke against the backdrop of public outcry over the company’s alleged abandonment of the project.
He said that work on the project slowed down significantly on the section of the road awarded to the company due to the nonpayment by the federal government.
He regretted that the company could no longer sustain work on the project through bank facilities.
Mr Asuquo also said that the claim that the company abandoned the project was misleading, pointing out that the company had continued work to ease traffic and reduce travel time, “even without payment.
“Sematech’s situation is verifiable. No contractor can effectively execute a major project without receiving funds from the awarding authority. If the Federal Government releases payment today, the company can complete its section of the project within two years,” he said.
Mr Asuquo also said that the payment of compensation to communities affected by the project was not Sematech’s responsibility but the sole responsibility of the federal government, in collaboration with the concerned state governments.
“Sematech had made several efforts to ensure compensation issues were addressed through the appropriate government channels,” he said.
He urged the public to direct compensation-related demands to the relevant federal and state authorities, not to the contractor.
Mr Asuquo further said that the contract was awarded by the previous administration and that delays under the present administration were “procedural, not deliberate”.
He called for people’s patience, saying that the company remained committed to completing the project once payments were made. He appealed to the federal government to release funds to expedite and improve the work on the road.
Meanwhile, a federal comptroller of works, Olayinka Onafuye, confirmed that Sematech had not left the site, although the work was slow.
“Sematech has almost completed one lane of the road allotted to it. Once compensation is paid and the indigenes vacate the affected corridors, work will continue on the other lane,” Mr Onafuye said.
The Calabar-Itu road, which connects Akwa Ibom and Cross River, has suffered protracted dilapidation, while its rehabilitation has lingered for many years.
A N185 billion contract for the rehabilitation of the road was awarded in 2021 to four companies, including Sematech.
(NAN)
We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.
More from Peoples Gazette

States
Independence: NBA urges Nigerians to expect better future
The NBA said that ordinary Nigerians should be deriving benefit from the subsidy removal rather than hardship.

Agriculture
FG tasks ECOWAS on leveraging financing strategies for agroecology
The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Politics
Katsina youths pledge to deliver over 2 million votes to Atiku
“Katsina State is Atiku’s political base because it is his second home.”

States
Sokoto approves N6.12 billion for nine UBEC prototype schools, mosque rehabilitation
Mr Muhammad-Achida added that the council had approved N230.6 million for the rehabilitation of Kuppa Juma’at Mosque in Gidan Sauro area.

States
CILT urges govt to digitise transport, boost agricultural logistics
The institute said these measures would reduce operating costs, improve efficiency and accelerate economic growth.

States
Edo govt identifies 129 gully erosion sites for urgent intervention
Mr Igiebor said the commission identified the ecological sites during its statewide assessment tour of 16 local government areas.

Heading 1
PDP hails court judgment reinstating Adebutu as Ogun governorship candidate
The party said the “ruling is a triumph of due process over administrative aberration.”

Faith
NCPC to flag off 2026 pilgrimage on November 23, months after suspension over Israel war
Mr Adegbite said pilgrimage is not a jamboree, adding that the commission had changed the dynamics.

States
Sokoto govt awards N5.5 billion contract to end 10-year blackout in four LGAs
The commissioner also said the state government awarded a contract worth N988.9 million to rehabilitate Government Technical College, Binji.