FG satisfied with quality, pace of work on Lagos–Ibadan Expressway: Umahi

Mr Umahi, however, directed the contractor to ensure the project was completed by the end of January.

• January 13, 2026
Lagos–Ibadan Expressway
Lagos–Ibadan Expressway(Credit: Peoples Gazette)

Works Minister Dave Umahi has expressed satisfaction at the quality of rehabilitation and expansion work on Section 1 of the Lagos-Ibadan Expressway.

The section starts from the Sagamu Interchange and ends at the Iperu Junction, both in Ogun. The project covers 12km with rigid pavement, five pedestrian bridges, four ramps, and three underpass routes.

Mr Umahi, during an inspection of the ongoing rehabilitation of the section of the road, said, ”I am very satisfied with the quality of work and the speed of work.

“We paid only 30 per cent  of the contract amount for this job, but I can assure you that they have done over 50 per cent of the job.”

He, however, directed the contractor to ensure the project was completed by the end of January.

Mr Umahi also directed the contractor to do the shoulders with laterite, where rigid pavements had been done.

“Whether it is in the bill or not, we are not paying for it. It is called protective work.

“There must be protective work to the edge of the pavement—a minimum of 1.5m if there is an embankment—before they descend with a two-to-one slope of embankment.

“The reason is to protect the pavement. If you don’t, water will start getting into it, and it will break.”

He directed the contractor to start the drainage where it should and to begin installing solar lights.

“By the end of this month, we should have everything about this 24km road fully completed,” he said.

Mr Umahi also inspected the 48km Benin-Ofosu-Ore-Sagamu dual carriageway. The project starts at Iperu junction and ends at Ajebandele, linking Ogun with Ondo and extending into the eastern part of Nigeria.

According to the minister, the Ore-Benin Road had been in good condition.

“From Benin to Summit Junction in Asaba is being done by a concessionaire, African Plus. By next week, I am going to evaluate that job and whether the concession is working.

“If it is not working, we will make a decision because we have very terrible news during December about the way the road was totally impassable,” he said.

Mr Umahi said the federal government intended to rehabilitate the entire stretch of the road from Sagamu to Asaba.

”The little push on 11km by two from Summit Junction in Asaba down to the Head Bridge is being reconstructed by Heartland,” the minister said.

He commended the contractor handling the Benin-Ofosu-Ore-Sagamu dual carriageway reconstruction and expansion for a good and fast job.

“I have had to go and examine the mixture of the concrete. I have seen the method of reconstruction. It was excellently done.”

Mr Umahi, however, directed the contractor to pull down the median and do a better one.

(NAN)

We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.

More from Peoples Gazette

farmers

Agriculture

FG tasks ECOWAS on leveraging financing strategies for agroecology

The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Katsina State

Politics

Katsina youths pledge to deliver over 2 million votes to Atiku

“Katsina State is Atiku’s political base because it is his second home.”

Lagos flooding

Lagos

Ibeju-Lekki council begins flood control interventions in communities

He said the council had deployed swamp buggies, drainage-clearing equipment and pumping machines to tackle flooding in communities across the LGA.

United States President Donald Trump

World

Trump vows U.S. control of Strait of Hormuz amid escalating tensions

“We are going to guard it. We are going to get paid,” Mr Trump said.

A medical lab technician at work

World

University of Oxford develops new Ebola vaccine 

The vaccine would be assessed for safety and immune response in 50 healthy adults in the UK aged between 18 and 55.

Maj.-Gen. Adamu Laka

NationWide

Insecurity: Nigeria adopts victim-centred reintegration plan to strengthen communities

The national coordinator of the National Counter Terrorism Centre (NCTC), Maj

Peter Obi

Education

Suspension of WAEC, NECO fee hike victory for Nigerians, says Obi

“Education is a fundamental right and a public good, not a source of government revenue,” he said.

businessman Adimike Godwin

Abuja

Police arraign three over alleged murder of Abuja businessman Adimike Godwin

The court adjourned the case until September 30 for further proceedings.