Ushafa-Bwari Road: Wike exposes FCDA contract variation jump from N50 billion to N200 billion

“I have never seen a thing like this in my life. What we see in FCDA contract variations from N10 billion to N119 billion and from N50 billion to N200 billion is alarming.”

• September 8, 2023
WIKE WITH FCT OFFICIALS
FCT minister Nyesom Wike with FCT Officials [Credit: FCT Administration Abuja/Facebook]

FCT minister Nyesom Wike has rejected the repeated variations of the Ushafa-Bwari road project contract fee.

Mr Wike revealed this while briefing journalists after a visit to the project sites along with FCT minister of state Mariya Mahmoud and other government officials in Abuja on Thursday.

He described the consistent variation of the contract cost of the project as “very embarrassing,” stressing “this is not what we are going to take.”

Mr Wike added, “The job was awarded in 2017 at N20 billion. In 2020, the contract was revised to N50 billion. As I speak to you, they have paid about N50 billion and what is outstanding is about N900 million. Now they are telling us that the N900 million is not enough to complete a job they said had reached 90 per cent completion.”

The FCT minister added, “Therefore, asking for another variation, we are not going to accept. Even the engineering services, we are going to overhaul the system.”

The minister complained of many variations in contract amounts handled by the Federal Capital Development Authority, which he described as “worrisome.”

“I have never seen a thing like this in my life. What we see in FCDA contract variations from N10 billion to N119 billion and from N50 billion to N200 billion is alarming, and I am not going to accept this,” said Mr Wike.

The minister visited the rehabilitation of Lower Usuma Dam Water Works, Gurara Road in Bwari, and expressed displeasure on the delivery of the water project.

The minister said he was told that the project was awarded as an emergency contract but realised on getting to the project site that it had not been awarded fully.

He said he found out that what was given to the contractor was a letter of intent in August 2022.

“I knew the importance of this project in supplying water to our people within the city and its environs. Water is very important, and so I have directed that the project is no longer an emergency,” said Mr Wike.

Mr Wike also mentioned that the project would be re-awarded, adding that his office would supervise the procurement process and invite other companies to bid.

(NAN)

We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.

More from Peoples Gazette

Nigerian Bar Association

States

Independence: NBA urges Nigerians to expect better future

The NBA said that ordinary Nigerians should be deriving benefit from the subsidy removal rather than hardship.

farmers

Agriculture

FG tasks ECOWAS on leveraging financing strategies for agroecology

The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Katsina State

Politics

Katsina youths pledge to deliver over 2 million votes to Atiku

“Katsina State is Atiku’s political base because it is his second home.”

Domestic violence

States

Kwara records 122 cases of domestic violence

The NHRC coordinator said the cases were not limited to physical assault but included emotional, sexual and economic abuse.

Wike 

Politics

Wike charges Gwagwalada residents to go all-in for Tinubu, APC candidates

Mr Wike urged residents not to treat election day like any ordinary day but to go all out for Messrs Tinubu, Aduda and Chiya.

World

Russia backs Ghana’s application to join BRICS as partner country

Russia has announced its support for Ghana’s application to join the BRICS economic bloc as a partner country.

Africa

Guinea inaugurates first gold refinery

Mr Sylla said the government’s current objective is to refine 30 per cent of its gold production.

World

Dutch prosecutors offer €2 million for capture of fugitive cocaine kingpin Bolle Jos

Mr Leijdekkers was sentenced in absentia to 24 years in prison by a Dutch court in 2025 for smuggling more than seven tonnes of cocaine.

Health

Kano traders arrested for altering expiry dates on milk

Mr Garba-Muhammad said sustained collaboration between the council and market associations is essential to protecting consumers.