FG terminates underperforming Abuja-Lokoja road contracts

The federal ministry of works has terminated the underperforming Abuja-Lokoja road contracts following an exhaustive performance review.
The minister of works, David Umahi disclosed this on Wednesday in Abuja while briefing journalists on the outcome of the meeting held with the Ministry and selected contractors.
He said the contractors are working on the Lokoja-Shintaku-Dekina and reconstruction of Okene-Ajaokuta road corridor in Kogi state.
Mr Umahi, who was represented by Mohammed Ahmed, director, Press and public relations, revealed that some of the contracts were mutually terminated.
He listed the contracts to include: the provision of culverts and drains at flood prone areas on the Federal Road Network in the North-Central Zone: Section 2, Abuja – Lokoja.
He said the contracts done on rigid pavement are being handled by Messrs Sadogi Nigeria Ltd. was awarded on April 4, 2024.
The minister said that only 39.04 per cent was completed with 112.88 per cent time elapsed.
He said the contract also included the rehabilitation of Abuja – Lokoja Section 4A: CH. 23 + 400 – CH. 26 + 400 RHS in Kogi, being handled by Messrs. Venus Construction Nigeria Ltd.
Mr Umahi said the project, which was awarded on July, 13, 2024, only 33.79 per cent was completed with 131.15 per cent time elapsed.
“There was mutual termination of the contract based on effusion of time.
“The contractor should work within the limit of the advance paid to them after which final determination account is to be carried out,” he said
Mr Umahi also identified the contract for the rehabilitation of Abuja–Lokoja Section IVB (Flooded Section, CH.23+400 – CH.26+395) LHS Contract No. 8490 being handled by Messrs. Sailthrough Engineering Service Ltd.
He said the ministry decided that the contractor should immediately submit a letter of commitment to complete the project on or before Dec.20, adding that the contractor had complied, even when the ministry was owing.
The minister also listed the contract for the reconstruction of Okene-Ajaokuta-Itobe road in Kogi State with contract No. 7648 being handled by Messrs. CCECC Nigeria Ltd.
He said the contract awarded on November 18, 2022, only 2.02 per cent was completed with 146.92 per cent time elapsed.
He said there was mutual termination of the contract based on effusion of time.
“The contractor should work within the limit of the advance paid to them after which final determination of account is to be carried out.
“There is also mutual termination of supervisory consultancy services because of lack of funding,has also been directed,” he said.
The minister said that the ministry also decided that the contract for the rehabilitation of Lokoja-Shintaku-Dekina-Ayingba road, contract No. 7239 being handled by TEC Engineering Company Nigeria Ltd should go the way of others
“It was awarded on February 3, 2022. Only 1.04 per cent was completed with 188.77 per cent time elapsed,” he said.
He, however, said that the ministry added mutual termination of supervisory consultancy services because of no funding.
He explained that Messrs. Geld/ Triacta Nigeria Limited (JV) handling the reconstruction of existing pavement and completion of additional pavement on dualisation of the Abuja – Lokoja highways Section III: Abaji – Koton Karfe has been ordered to resume work within seven days at the bad sections of the road.
The minister commended Messrs. JRB Construction Nigeria Limited for their performance on the rehabilitation works on Section 1 of Abuja – Lokoja road and directed that the project be completed before December 10.
“We have directed that all outstanding works from Abuja to Lokoja, including all mutually terminated projects, be compiled for immediate emergency intervention,” he said.
Mr Umahi thanked President Bola Tinubu for his kind interventions on the entire stretch of the 179km x 2 (358km) Abuja-Lokoja road.
The minister apologised to all road users on the Abuja-Lokoja expressway to bear with the ministry.
He said the inconveniences being experienced on the road were due to multiple ongoing intervention projects.
He assured that the work would be completed soon.
(NAN)
We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.
More from Peoples Gazette

Agriculture
FG tasks ECOWAS on leveraging financing strategies for agroecology
The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Politics
Katsina youths pledge to deliver over 2 million votes to Atiku
“Katsina State is Atiku’s political base because it is his second home.”

States
Olubadan lauds Tinubu on release of Oriire kidnap victims, urges rehabilitation
“As a follow-up to this development, the government must ensure that all communities bordering the National Park are fully secure,” he said.

Heading 1
Iran’s new supreme leader vows revenge over father’s assassination by U.S.-Israeli forces
“We pledge to avenge the blood of the martyred leader and all the martyrs of these two wars from the criminal and disgraced killers,” he said.

Heading 4
Trump administration subpoenas New York Times journalists over Air Force One story
The subpoenas seek to compel the reporters to testify before a federal grand jury in Manhattan.

Heading 2
Klopp agrees to replace Nagelsmann as Germany coach
Nagelsmann resigned last week as the men’s national team coach following Germany’s shocking exit from the 2026 FIFA World Cup.

Health
FG expands cancer funding, local drug production
“We are trying to domesticate expensive treatments by producing much-needed medicines locally and translating global research into action in our clinics,” he said.

Heading 3
Remi Tinubu begs Asake, Davido, Burna Boy to come rescue poor Nigerians from hunger
The first lady stated that buying exotic cars is good, but noted that the singers can still establish foundations to assist the struggling population.