Phase 1 of ongoing national library project for completion June 1, says education minister

The Minister of Education, Dr Tunji Alausa, has said the first phase of the National Library will be completed by June.
Mr Alausa stated this on Wednesday during an on-the-spot monitoring and assessment of the national library project in Abuja.
He stated that the first phase of the project would include two basement levels, the ground floor, first and second floors, as well as all external works, including perimeter fencing.
Mr Alausa explained that variations in the bill of quantities contributed to the delay in completing the project.
“There have been numerous variations in this project. Even the contractor’s quotation from a few years ago, which was about N90 billion, contains several conflicting elements,” he stated.
Emphasising that completing the national library was a priority, he noted that other pressing projects also required funding.
“If we were to re-evaluate the cost today, it would run into hundreds of billions of naira. However, we have adopted an innovative approach to move the project forward, starting with the completion of phase one,” he said.
Mr Alausa assured that there were sufficient funds available for the project but stated that final costing was still pending, based on the bill of quantities to be prepared by the consultant.
“We are dividing the project into phases. For the first phase, we will commence work on-site on or before June 2025,” he added.
The minister commended President Bola Tinubu for his political support and commitment to ensuring the project was completed promptly.
Expressing concern over the prolonged delay, he highlighted how other national monuments had been completed long ago while the National Library remained unfinished.
“We have three national monuments in Abuja—the National Mosque, the National Ecumenical Centre, and the National Library.
“Ironically, almost 40 years after the National Mosque and the Ecumenical Centre were completed; we are still struggling to complete the National Library.
“This library is a crucial part of our human capital development, and now, with the highest political will, we are committed to pushing this project forward,” he stated.
The National Librarian, Prof. Chinwe Anunobi, assured that efforts were underway to meet the deadline set by the minister.
“A directive has been issued for the contractor to return to the site, and we are committed to ensuring that the deadline is met,” she said.
She emphasised the importance of the national library, describing it as a repository of the nation’s heritage, including documents, reports, monographs, books, research papers, and newspapers.
The national library was designed in 1981. Construction, however, began in 2006 and was initially expected to be completed by 2008. Work stalled at the site in 2012, leading to years of delay.
(NAN)
We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.
More from Peoples Gazette

Agriculture
FG tasks ECOWAS on leveraging financing strategies for agroecology
The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Politics
Katsina youths pledge to deliver over 2 million votes to Atiku
“Katsina State is Atiku’s political base because it is his second home.”

Africa
Eleven children killed, 19 injured in Algeria orphanage fire
President Abdelmadjid Tebboune described the tragedy as a huge loss.

Heading 2
Kano empowers 1,900 butchers, to establish cottage industry hubs
He said the government had already made provision for the establishment of the hubs in the 2026 budget.

Heading 3
2027 Elections: Police commence recovery of illegal arms nationwide
Mr Kokumo said the centre had destroyed more than 16,000 unserviceable weapons since its inception.

Heading 5
Court restrains FRSC from operating on Kano township roads
Mr Hikima sued the commission for unnecessarily stopping, searching and questioning him and other motorists.

Heading 5
White House teleprompter operator rakes in over $100,000 betting on Trump’s speeches: Report
Investigators discovered Mr Perez placed bets on more than a dozen of Mr Trump’s speeches over a three-month period.

Hot news Home top
Kidnapped Kogi school principal, NECO official, students regain freedom
Gunmen, on Tuesday, abducted a principal, NECO official and students during exam in Kogi school.