Umahi gives November deadline for completion of Enugu-Port Harcourt expressway project 

He expressed dissatisfaction with the slow pace of work on the section. 

• October 31, 2025
Minister of Works David Umahi
Minister of Works David Umahi

The minister of works, Dave Umahi, has directed Arab Contractors handling the rehabilitation of the Enugu-Port Harcourt Expressway to complete the remaining 4.5-kilometres Abia section before the end of November.

Mr Umahi gave the directive on Friday in Aba after inspecting the progress of work on the project.

He expressed dissatisfaction with the slow pace of work on the section, warning that the contract would be revoked, if the deadline was not met.

“I am not happy with the progress of work on this 4.5-km out of the 112-km of the road.

“I am giving you a charge today. By the end of November, the entire laterite, sharp sand, and concrete work must be finished on this road.

“If it is not done, I will revoke the contract,” Mr Umahi said.

He assured the contractor of prompt payment, describing the  President Bola Tinubu-led administration as “a reliable partner that does not renege on its financial obligations.

“The president is not the type that will ask you to work and he will not pay you.

“You will be paid, because if we have paid you for the other sections, we will pay for this one too,” he said.

Mr Umahi praised Gov. Alex Otti of Abia for his unwavering commitment to the development of the state and for supporting the president’s infrastructure agenda.

“Governor, I thank you, especially your push for the development of Abia is unparalleled.

“The president has shown very serious attention to the affairs of the South-East, and road infrastructure is one of such,” he said.

He also commended the contractors for their integrity and quality of work, recalling how the company’s management had previously prioritised completing existing projects over taking new ones.

Mr Umahi further directed the Federal Ministry of Work’s Controller in Abia to ensure strict supervision, vowing to return to the site weekly to monitor progress.

“I will come back every week to look at it.

“Finish the sharp sand filling, finish the concrete work, let us be left with stone base and the binders,” he charged the company.

In his remark, Mr Otti affirmed his administration’s commitment to supporting federal projects for the benefit of the people of Abia.

He also pledged his administration’s full support to ensure the timely completion of the Aba segment of the Enugu-Port Harcourt Road.

He expressed satisfaction with the progress of work, saying that with only 4.5-km remaining on the project, the end was in sight.

He said that he had secured a commitment for the project to be commissioned by December.

“Whatever it takes, like the Honourable Minister said, I’m going to be coming here from time to time.

“I live here with you and if you need anything, please let me know,” Mr Otti said.

He commended the contractors for the quality of work done so far and hinted at the possibility of more projects for the company upon the successful completion of the current one.

Also, the zonal manager of Arab Contractors, Mohammed Elian, disclosed that only five per cent of work was left on the project, expressing commitment to its completion by December.

Mr Elian commended Abia government for the improved security situation in the state and lauded the minister for his efforts towards the project’s completion.

He said that the project’s scope  covered the road from Umuahia Tower to Aba Township and that the bulk of the work, particularly the dualisation, had been completed.

“What remains in the project is just 4.5-kilometres on one side, which is like five per cent of the entire project,” he said.

He said that his company had received directives from its management to deploy its “full force” to ensure timely delivery.

He acknowledged the promise of continued funding from the Federal Government which, he said, was crucial for completing the remaining work.

“By God’s grace (Inshallah), we will do our best to complete the project by December,” Mr Elian said.

Earlier, the controller, Federal Ministry of Works in Abia, Chidi Uwaeziozi, said that the Port Harcourt-bound lane of the road had reached an advanced stage of completion.

He also said that the entire Enugu-bound lane of the road had been fully completed.

“On the right-hand side, which is the Port Harcourt-bound lane, it is only remaining 4.5-km, covering both the main carriageway and the service lane,” Mr Uwaeziozi said.

He expressed strong optimism over the timely completion of the project ahead of the December date for its inauguration. 

(NAN)

We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.

More from Peoples Gazette

farmers

Agriculture

FG tasks ECOWAS on leveraging financing strategies for agroecology

The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Katsina State

Politics

Katsina youths pledge to deliver over 2 million votes to Atiku

“Katsina State is Atiku’s political base because it is his second home.”

ADC logo

States

ADC reaffirms confidence in Adamawa governorship candidate

Adamawa ADC passed d a vote of confidence in its governorship candidate, Omar Suleiman, ahead of 2027.

Heading 1

2027: Opposition not in disarray, we’re on top of our game, ex-presidential candidate Onovo says

Mr Onovo said the opposition was ahead of the ruling party despite the crisis over their candidacies on various political platforms.

NationWide

Troops rescue seven kidnap victims, kill two kidnappers

The troops also recovered arms, ammunition and other items in coordinated operations across Borno, Yobe, Benue and Plateau states.

Independent Petroleum Marketers Association of Nigeria (IPMAN)

Economy

Fuel price uncertainty forced marketers to halt supply temporarily: IPMAN

The Independent Petroleum Marketers Association of Nigeria (IPMAN) says uncertainty over petrol prices has forced many marketers to halt fresh purchases, leading to the temporary closure of some filling

Economy

Tinubu committed to investment in renewable energy, says presidential aides

He said Mr Tinubu is committed to investments in renewable energy development, human capital empowerment, clean energy innovation, and Nigeria’s Energy Transition Plan.

FLOODED FARM

Agriculture

Flooding may raise vegetable prices, Lagos farmers warn

“If we sold vegetables at lower prices before, they will now become more expensive because farmers must recover their losses,” she said.